Merryhill Complete Asbestos Removal Project in Portsmouth


Merryhill recently completed a large asbestos removal project at a former University of Portsmouth accommodation campus.

The Langstone campus in Milton, Portsmouth had a number of old accommodation blocks that required demolition prior to redeveloping the site.

Having been closed in 2018, the client had deemed the buildings to be beyond economical repair. To mitigate any risk of the buildings being misused while left unoccupied the University decided to demolish the buildings.

Merryhill were contracted to Hughes and Salvidge, the demolition contractor for the project.

Merryhill’s contract was to remove a number of both licensed and non-licensed asbestos materials from each of the 7 large blocks, including the clearance of a floor duct system. The floor duct network was found to contain asbestos insulation board (AIB) shuttering.

AIB High Level Fascia
AIB high level fascia panel behind UPVC cladding and bitumen felt

Along with the floor ducts, the other main notifiable asbestos had been found above all top floor windows by way of AIB fillet panels.

During the course of the removal process, it was found that further AIB was present to the external high level fascias around the perimeter of each building.

AIB fillet panel above window

Following the additional discovery of the fascia panels, Merryhill worked hard to ensure the overall project programme was not jeopardised.

Asbestos Removal Project in Hampshire

asbestos removal enclosure

Asbestos removal can be a difficult task in an unoccupied building, let alone a live working environment with adjacent offices in constant use. A recent asbestos removal project in Hampshire was just that.

The asbestos removal project in Hampshire involved the decontamination and removal of asbestos debris from seven rooms along a corridor prior to refurbishment. The concrete structural ceiling above a more modern suspended ceiling had once had asbestos insulation board (AIB) attached. Following an asbestos refurbishment survey, the ceiling void and modern grid system was found to have some AIB debris contamination.

The project required Merryhill to remove all the ceiling tiles, grid system and contaminated timbers above and environmentally clean the entire ceiling void area before the rooms could be reconfigured.

Works began by removing all of the ceiling tiles in each of the seven rooms, these were sprayed with a water surfactant mixture, prior to being wrapped in 1000-gauge polythene and disposed of as hazardous waste. The ceiling grid and lighting fixtures were cleaned and recycled for future use in the newly refurbished rooms once the asbestos had been removed. Upon removal of all suspended ceiling components and other items attached to the structural ceiling above, the contaminated timbers could then be removed.

Each of the timber battens were first encapsulated with ET150 paint and allowed to dry. This was to ensure any loose fibres were encapsulated prior to being pried away from the concrete ceiling above. All the contaminated timbers were placed on polythene sheets and sealed with cloth tape prior to disposal. Once all affected timbers were removed, each room then underwent a full environmental clean to remove any residual asbestos fibres.

Upon completion, the entire area was tested by a third party analytical company and a reoccupation certificate issued to the building owner.

In this project, Merryhill had to accommodate the needs of the client in ensuring some rooms on the opposite side of the corridor could be accessed during the works whilst ensuring adequate levels of segregation. Whilst this was not ideal as it made the working area slightly smaller, the enclosure was constructed in order to maintain access for workers and ensure our operatives could carry out the project in a safe manner.

Asbestos Removal Project in Surrey

Asbestos Floor Void

Merryhill was recently asked to look at an asbestos removal project in Surrey where ACMs had been discovered in a floor void. The contaminated area required all the asbestos to be removed prior to additional service pipes being run by other contractors.

Upon viewing the detailed asbestos refurbishment survey carried out by our surveying division (MATAC), Merryhill was successful in securing the project to remove asbestos pipe lagging and other asbestos residues.

Asbestos Pipe Lagging

Totalling an area of 150m2, this was only part of a much larger floor void that was also contaminated with asbestos, but outside of the project scope.

Prior to commencing work, our asbestos removal team had to seal the area above floor level to create the working enclosure. Once this had been built, then the necessary floor boards were removed in order to access the floor void below. Once the necessary floorboards were removed, the team incorporated the working area into the enclosure, sealing it from the rest of the floor void with 1000 gauge polythene.

Asbestos Lagging in Floor Void

Once the working area had been constructed and sealed, the team then carried out the asbestos removal and environmental cleaning of the contaminated area. All pipe lagging was removed using the SafeStrip RedBox injection system. All loose debris was sprayed with a water surfactant and either vacuumed using H-Class machines or placed directly into appropriate waste bags and sealed. As there were a number of disused pipes and other construction debris within the floor void, this was also disposed of as contaminated waste.

As the remainder of the floor void was to remain untouched, a semi-permanent barrier was constructed using 1000 gauge polythene and Corex. This barrier was installed to ensure the cleaned area did not become contaminated once again by the remaining floor void. As part of the clients’ asbestos management plan, the sealed area of cleaned floor void will be tested on an annual basis to ensure a tight seal remains. If future works are to take place within the floor void, then the client can be assured the cleaned area will not require re-visiting.

This staged approach to having asbestos removed from larger areas can be an affordable option to some clients, especially if the remaining materials are in a good condition and pose a low risk. In this case, it is the intention of the client to have the remaining areas completed at a later date.

Asbestos Demolition Survey in London

Asbestos Survey London

Prior to being redeveloped, a former factory required an extensive asbestos refurbishment and demolition (R&D) survey. Originally built in the early 20th Century, the factory in West London ceased operation in 2014. Since its’ closure, the site had gradually been cleared, ready for being transformed into a mixed used development consisting of commercial and residential properties.

Approached by our client to carry out a fully intrusive survey, the project posed some challenges which needed to be overcome. Given the scale of the buildings, it required not only a lot of manpower, but also coordination to ensure all areas were thoroughly covered. In addition to this, the main building needed to be split in terms of the survey required as only one part was covered by our clients’ scope of works, the other was being dealt with by another contractor. This meant an imaginary line was placed through the building, meaning Merryhill’s work was to only be carried out strictly on one side.

Various other buildings were part of the scope, including offices, warehouses and a large house. In total, over 50,000m2 of building were covered in producing the final report where 341 samples were carefully taken and sent for analysis in a laboratory, 96 returning a positive result. All types of asbestos were discovered upon analysis.

Speaking on behalf of Merryhill, Adrian Lynn, Surveyor who worked on the project said: “The project was a challenge, firstly given the scale of the buildings as the site is huge so a lot of planning was involved prior to getting on site to ensure the best use of time. It was a slightly odd situation with the imaginary line across the main building as not all of the site was being demolished. The project highlights Merryhill’s ability to cope with large, complicated surveys involving access equipment across multiple buildings of varying use.”

Removing Asbestos from Tower Blocks

Asbestos in Tower Blocks

Removing asbestos is a challenging task even in normal circumstances, with specialist techniques employed for different types of material, the skill and attention to detail required is very high in order to protect people from the harmful mineral. When asked to carry out asbestos removal from the outside of tower blocks, the challenge becomes even greater, with meticulous planning and a higher than normal level of health and safety considerations to be made.

As part of a major improvement plan across a Southampton social housing estate, Merryhill was invited to carry out the asbestos removal contract involving three separate tower blocks. The Dumbledon, Meredith and Hightown towers on the Thornhill estate were originally constructed in the 1950s/60s and are of an identical design. The regeneration scheme will see each of the blocks receiving a range of energy-saving improvements, including new windows, heating systems managed by tenants, coloured external wall insulation, new roofs and enclosed balconies. ECL Contracts, the facades division of British Gas is managing the project and invited Merryhill to tender for the asbestos removal element of the project.

After thorough surveys had been commissioned prior to the works commencing, asbestos was found to be present in a number of different areas across the Thornhill Towers, including external cladding and balcony panels.

Removing each of the different types of panel was a challenge as everything had to be removed from the outside and at height. All of the towers were 14 storeys high and the only means of access was by mast climbers which had been set up around each building.

Both the cladding and balcony panels were carefully removed and suitably wrapped in 1000-gauge polythene, sealed tight and stacked before being brought down to the crash deck and placed on a pallet. From here, the panels were lifted by telehandler and stored in locked asbestos skips before being transited to landfill. Because of the number of panels being removed, Merryhill had to keep a close monitor of the adjacent properties to ensure tenants did not open any windows for the duration of the works. Although asbestos cement is a relatively low risk material and the removal method is done under wet conditions to minimise any fibre release, the additional protection from keeping windows closed during the works was felt a necessary additional precaution.

Overall, the project was a resounding success with all the asbestos removed from the exterior of each of the towers. Work has now begun on transforming the buildings to improve their energy efficiency, safe in the knowledge that all of the external asbestos has now been removed.

Asbestos Removal for Social Housing

Asbestos is a problem probably faced by all local authorities across the UK. With thousands of buildings containing the substance in various different forms, the challenge faced by councils up and down the country is how best to manage their own individual circumstances and remove asbestos containing materials (ACMs) where possible as part of ongoing maintenance. Becoming a strategic partner to local authorities and aiding them in the efficient and safe removal of asbestos from their properties is critical to providing a safer housing stock for tenants.

Removing asbestos is often the most simple part of the partnership as Merryhill has been successfully carrying out similar work since 1980. Empathising and communicating with tenants, achieving KPIs set by the customer, dealing with emergency call-outs and working with other specialist trades such as analysts, plumbers, electricians and maintenance contractors is often the biggest challenge. Timing is key, along with great organisation and the ability to prioritise projects, especially when the volumes increase suddenly.

Communication is key!

Asbestos is often a taboo subject, especially when people do not understand the potential dangers associated with different forms of ACM. Communicating with tenants and other stakeholders involved in the process of removing asbestos is a key factor when working in partnership with a council, housing association or local authority. Letting tenants know what to expect in advance of any works being carried out and providing reassurance where necessary is paramount to achieving the best possible outcomes.

Communication with other trades working on the project is another key activity when carrying out asbestos removal in social housing as often it is part of a wider scope of works. Kitchen and bathroom refurbishments are the most frequently attended areas as often these contain the most different types of ACM including Artex ceilings,  asbestos insulating board, pipe lagging and asbestos vinyl floor tiles. Attending site at the correct time is key as often other trades are waiting to carry out their own work once an area has been made safe and decontaminated.

Since winning the framework contract to remove asbestos from social housing stock for Waverley Borough Council last autumn, the statistics so far have been impressive. Aside from the sheer volume of works carried out, feedback from tenants has been very good with very positive comments received each month on our work, professionalism and attention to detail.